Decision Guide Basics

Need Help?

PRO-9
Approve STIP with respect to Conformity and Fiscal Constraint

Description: In order to meet federal requirements, the STIP must meet conformity and fiscal constraint, where required.

There is information developed in prior key decisions that informs this step.



  • Basics
  • Integration
  • Decision Making Questions
  • Case Study Examples
  • Technical Support
  • Special Topics

Purpose

To validate that the approved TIP/STIP meets requirements related to air quality conformity and fiscal constraint, where required.

Outcome

TIP/STIP that meet all state and federal requirements.


Partner Roles

MPO

Observer (urban), No Role (rural)

Observes the approval of the STIP (including the metropolitan TIP) with respect to conformity and fiscal constraint

FHWA

Decision Maker

Approves the STIP with respect to conformity and fiscal constraint

State DOT

Advisor

Provides information required for approval of the STIP as needed

Resource Agency

Decision Maker

USEPA approves STIP with respect to air quality conformity. Other agencies have no role.


Process

Integration Type

Integration Description

Land UseNone.None.
Air QualityNone.None.
Natural EnvironmentNone.None.
Capital ImprovementNone.None.
Safety and SecurityNone.None.
Human EnvironmentNone.None.

Linkages to other Phases of Transportation Decision Making

Key Decision

What is Linked?

Purpose of Linkage

To Environmental Review

ENV-6 - Approve Full Range of Alternatives

Information from the TIP regarding a project description, logical termini, and funding identified for the project.

To inform, but not constrain, the development of the full range of alternatives for environmental review.

ENV-8 - Approve Draft EIS with Conceptual Mitigation

Funding for mitigation programmed in the STIP.

To inform partners of the sufficiency of funds for avoidance, minimization and mitigation programmed in the STIP.

ENV-12 - Reach Consensus on Avoidance and Minimization for the LEDPA

Funding for mitigation programmed in the STIP.

To inform partners of the sufficiency of funds for avoidance, minimization and mitigation programmed in the STIP.


Policy Questions

Questions about purpose and roles

No specific questions.

Questions about stakeholders

What did we do in response to the feedback from the stakeholders?

What were the commitments of the stakeholders? Are they still being upheld?

Questions about the transportation process supporting the decision

Are the individual MPO TIPs that have been incorporated into the STIP consistent with their LRTP fiscal constraint?

For areas outside of MPO boundaries, does the STIP meet air quality conformity requirements?

Is the STIP fiscally constrained?

Where appropriate, are the individual MPO TIPs incorporated into the STIP consistent with the LRTP conformity?

Questions about other phases

No specific questions.

Questions about non-transportation sectors/processes

No specific questions.

Questions to Gather Stakeholder Interests

What are your comments on the Draft STIP?

Questions to Incorporate Stakeholder Interests

What did the stakeholders tell us?


Case Study Example(s):

None.

Supporting Data for the Key Decision

InfoThe following is a list of data needed to support the key decision. Practitioners collect this information for decision makers to consider. You may add to this list using the comment box at the bottom of the page.

From other phases of transportation decision making

Long Range Planning

Conformity analysis and approvals by MPOs and State.

Programming

No Specific Data

Corridor Planning

No Specific Data

Environmental Review

No Specific Data

From other sectors and processes

Land Use

No Specific Data

Air Quality

No Specific Data

Natural Environment

No Specific Data

Capital Improvement

No Specific Data

Safety and Security

No Specific Data

Human Environment

No Specific Data

From the transportation technical process supporting this key decision

Validation of fiscal constraint.

From stakeholder collaboration

Stakeholder input and consideration of the Draft STIP

Public input and State’s consideration of the Draft STIP

Supporting Tools and Technology

Category

Detail

Gathering

Commenting Tools: Tools to gather comments




Key Decision Relationship to Other Topics

None.