Decision Guide

Need Help?

PRO-3
Approve Project List Drawn from Adopted Plan Scenario or Solution Set

Description: This key decision establishes the list of projects drawn from the long range plan or corridor planning process that will be considered for funding in the TIP. Improvements to be funded with non-transportation revenue are not included in this project list.

There is information developed in prior key decisions that informs this step. In order to effectively execute this key decision there is essential information created at LRP-8 for projects included in the adopted preferred scenario consistent with revenue availability and COR-9, where applicable. PRO-1 provides revenue sources to be applied to project list/validated from the long range plan.



  • Basics
  • Integration
  • Decision Making Questions
  • Case Study Examples
  • Technical Support
  • Special Topics

Purpose

To create a list of projects to consider for funding drawn primarily from the adopted plan scenario and/or adopted priorities in corridor planning.

Outcome

An approved list of projects to consider for funding that provide as much detail as currently available.


Partner Roles

FHWA

Observer

Observes the identification of specific projects from the adopted plan scenario

MPO

Decision Maker

Approves projects that are drawn from the adopted preferred scenario of the LRTP to maintain fiscal constraint

Resource Agency

Observer

Observe the project list drawn from the adopted plan scenario to inform conservation planning of future potential projects.

State DOT

Advisor

Provides support for project identification as needed


Process

Integration Type

Integration Description

Land Use and Smart GrowthNone.None.
Air Quality ConformityNone.None.
Natural Environment and the IEFData To IEF Step 9 - Update Regional Ecosystem Framework & Plan The project list drawn from the adopted plan scenario should inform any updates to the ecological plan.
Capital ImprovementNone.None.
Safety and SecurityNone.None.
Human EnvironmentNone.None.
Economic DevelopmentNone.None.
Greenhouse GasNone.None.

Linkages to other Phases of Transportation Decision Making

Key Decision

What is Linked?

Purpose of Linkage

To Long Range Transportation Planning

LRP-8 - Adopt Preferred Plan Scenario

Projects included in the adopted plan scenario consistent with revenue availability

To inform the project list created at this key decision

From Corridor Planning Studies

COR-7 - Adopt Preferred Solution Set

Improvement projects identified in the adopted solution set with their anticipated costs

To inform the project list in the programming/fiscal constraint phase

COR-9 - Adopt Priorities for Implementation

The project priority list developed in the corridor plan

To ensure that the TIP reflects the desired prioritization of the corridor plan


Policy Questions

Questions about purpose and roles

No specific questions.

Questions about stakeholders

How was the public involved in selecting the projects included on the project list?

Questions about the transportation process supporting the decision

Have federal regulations been satisfied?

Questions about other phases

To what extent does the project list address the transportation deficiencies as identified in the LRTP and/or corridor plan?

Was project readiness considered?

Questions about non-transportation sectors/processes

No specific questions.

Questions to Gather Stakeholder Interests

None.

Questions to Incorporate Stakeholder Interests

None.


Case Study Example(s):

None.

Supporting Data for the Key Decision

InfoThe following is a list of data needed to support the key decision. Practitioners collect this information for decision makers to consider. You may add to this list using the comment box at the bottom of the page.

From other phases of transportation decision making

Long Range Planning

LRP-8: Projects included in the adopted preferred scenario with associated costs and consistent with revenue availability

Programming

PRO-1: List of revenue sources identified

Corridor Planning

COR-7: Improvement projects identified in the adopted solution set with their anticipated costs

COR-9: Projects included in the adopted preferred scenario consistent with revenue availability

Environmental Review

No Specific Data

From other sectors and processes

Land Use and Smart Growth

No Specific Data

Air Quality Conformity

No Specific Data

Natural Environment and the IEF

No Specific Data

Capital Improvement

No Specific Data

Safety and Security

No Specific Data

Human Environment

No Specific Data

Economic Development

No Specific Data

Greenhouse Gas

No Specific Data

From the transportation technical process supporting this key decision

List of projects with associated costs and potential revenue sources from adopted scenario or solution set

Information on project readiness and potential support by partners and stakeholders

From stakeholder collaboration

No Specific Data

From public private partnership

No Specific Data

Supporting Tools and Technology

Category

Detail

Communication

GIS Tools: Used to communicate geographic extent of project list. Effective tools for this key decision include web-based services which can display area maps with GIS overlay layers (i.e. Google Earth)

Gathering

GIS Tools: Additional features to accept feedback from stakeholders and public




Key Decision Relationship to Other Topics

None.